Revell House Project Report |
Construction:
12/17/2014 Architects visited the site. Concrete slab near completion with wire mesh and vapor barrier. The under slab drain pipes were roughed in. The Basement wall parging in progress. A construction progress meeting was held at the Baha'i Center with the contractor to discuss the work and next milestone. 12/24/2014 Contractor had vacation from 24th to 28th and started back on the 29th. Presentation: 12/27/2014 The Phoenix Assembly graciously allowed Massoud and Roya, as Philadelphia Baha'i Community representatives to make a short 5-minute presentation about the Revell House at the Grand Canyon Baha'i Conference in Phoenix, AZ during the Saturday morning general session. They also provided a table at the main hall where the Revell House photos and information were displayed and about 200 Revell House leaflets were distributed during the 3-day conference. Contacts were made with the LSAs of Phoenix and Scottsdale as well. The display is left in Scottsdale for further use. Construction: 12/28/2014 Contractor sent second invoice. Architects forwarded the invoice to the treasurer. 12/31/2014 Architects visited the site. Wall, roof framing and sheathing with insulation and building wrap of the laundry room completed. Parging of basement walls still in progress. 1/2/2015 Architects took some measurements of the completed new work as well as existing windows for verification. Visited and contacted a number of window manufacturers to get quotes for upgraded windows and doors. 1/4/2015 Prepared revised window schedule sent to manufacturers. Responded to contractors email questions. 1//8/2015 On-going communication with contractor. Verified status of work. Contractor sent revised Invoice #2. Roof underlayment of the addition is installed. A meeting will be held soon to discuss progress of work and next milestones. |