Philadelphia Bahá'í Community
  • Home
  • The Bahá'í Faith
    • The Bahá'í Teachings
    • Central Figures
    • An ever-advancing civilization
    • Bicentenary Celebration of the Birth of Baha'u'llah
    • 'Abdu'l-Bahá's Visit
  • Community-building activities
    • Devotional Gatherings
    • Study Circles
    • Junior Youth Groups
    • Children's Classes
  • Calendar of Activities
    • Request Use of the Baha'i Center
  • Revell House
  • New To Philly
  • Contact Us
  • Directions
  • Links
  • Education is Not a Crime
  • Center scheduler
    • Link Page
  • Library
  • Request Use of the Baha'i Center
  • Philadelphia Baha’i Bulletin
  • Treasurer’s Office
    • World Conference
  • Fillable Check Request
  • Caretaker App
  • Caretaker Application

Revell House Project Report

Latest Report
Construction:

12/17/2014   Architects visited the site. Concrete slab near completion with wire mesh and vapor barrier. The under slab drain pipes were roughed in. The Basement wall parging in progress.

A construction progress meeting was held at the Baha'i Center with the contractor to discuss the work and next milestone.

12/24/2014 Contractor had vacation from 24th to 28th and started back on the 29th.

Presentation:

12/27/2014 The Phoenix Assembly graciously allowed Massoud and Roya, as Philadelphia Baha'i Community representatives to make a short 5-minute presentation about the Revell House at the Grand Canyon Baha'i Conference in Phoenix, AZ during the Saturday morning general session. They also provided a table at the main hall where the Revell House photos and information were displayed and about 200 Revell House leaflets were distributed during the 3-day conference. Contacts were made with the LSAs of Phoenix and Scottsdale as well. The display is left in Scottsdale for further use.

Construction:

12/28/2014 Contractor sent second invoice. Architects forwarded the invoice to the treasurer.

12/31/2014 Architects visited the site. Wall, roof framing and sheathing with insulation and building wrap of the laundry room completed. Parging of basement walls still in progress.

1/2/2015 Architects took some measurements of the completed new work as well as existing windows for verification. Visited and contacted a number of window manufacturers to get quotes for upgraded windows and doors.

1/4/2015 Prepared revised window schedule sent to manufacturers. Responded to contractors email questions.

1//8/2015 On-going communication with contractor. Verified status of work. Contractor sent revised Invoice #2. Roof underlayment of the addition is installed. A meeting will be held soon to discuss progress of work and next milestones.